Time and Effort

Day
Deven
Jon
Group
11/28/2024
Update Website (2 hours)
11/27/2024
11/26/2024
11/25/2024
Work on report soft draft (3 hours)
Soft draft formatting (1 hour)
11/24/2024
11/23/2024
Reinforce weak points on frame (2 hours)
Make final adjustments to frame (3 hours)
11/22/2024
Work on soft draft (2 hours)
Week 13
11/21/2024
Work on report soft draft ( 5 hours)
Bring together pieces of soft draft and format (3 hours)
11/20/2024
Work on backplate reinforcement (3 hours)
Addressed soil moisture’s effect on the NPK sensor. (5.5 Hours)
11/19/2024
Backplate construction and attachment (3 hours)
Continue writing report soft draft (1.5 hours)
11/18/2024
Researched and identified issues with the DHT sensor library causing system delays. (2 Hours)
11/17/2024
Implemented a non-blocking approach using millis(). (1 Hours)
11/16/2024
11/15/2024
Reconfigure wiring to accomodate new sensor positions (2 hours)
Identified the blocking behavior caused by the use of delay() in the code. Began researching alternative approaches to resolve timing issues (2 Hours)
Week 12
11/14/2024
Update Website (1 hour)
Work on hardware and software bugs ( 7 hours)
11/13/2024
Work on wiring and hardware issues with Arduino Mega (6 hours)
Programmed lights and pumps to respond to manual controls. (2 Hours)
11/12/2024
Work on wiring, tubing, and NPK sensor movement ( 5 hours)
Resolved NPK sensor conflicts with the display library. Identified serial communication issues. (3 Hours)
Get NPK sensor functional (4 hours)
11/11/2024
11/10/2024
Tested the new EC sensor. Tried multiple libraries, adjusted baud rates, and rechecked wiring. (4 Hours)
11/09/2024
NPK sensor testing with the Pi3 (3 hours)
Addressed a graphical bug on the display where old data overlapped new data. (4 Hours)
11/08/2024
Began troubleshooting touchscreen display. Increased the size of the manual control touch areas to improve responsiveness. (1.5 Hours)
Week 11
11/07/2024
Update Website (1 hour)
Configured Blynk mobile app and completed a similar layout (2.5 Hours)
Review progress before meeting (1 hour)
11/06/2024
Tested Blynk connectivity to Arduino R4 (2 Hours)
11/05/2024
Work on report (2 hours)
Began setup for companion app using Blynk (2 Hours)
11/04/2024
Work on report (2 hours)
Evaluated response from sensor on Arduino Mega (3 Hours)
Discuss Arduino Mega (1 hour)
11/03/2024
Planter guiderails and water bucket modifications (2 hours)
Tested NPK sensor on the Arduino Mega with various codes and libraries (2 Hours)
11/02/2024
Stepper Motor Fine Tuning (2 hours)
11/01/2024
Plan goals for the week (1 hour)
Week 10
10/31/2024
Update website (2 hours)
Ran additional tests comparing RS485 and Arduino outputs. (2 Hours)
10/30/2024
Clean up stepper motor code (1 hour)
Set up the RS485 adapter following online wiring instructions. Explored alternative serial monitoring software, Serial Monitor Device Tool. (5 Hours)
Get together in person and work on parts in tandem (5 hours)
10/29/2024
Continued Stepper motor testing (3 hours)
Configured PCF8574 to work with DHT library ( 4 hours)
10/28/2024
Stepper Motor testing (3 hours)
10/27/2024
Investigated discrepancies between the sensor manual and the actual specifications (2 Hours)
10/26/2024
Work on water level sensors (3 hours)
Tested multiple codes and configurations from various forums. (4 Hours)
10/25/2024
Researched online forums and resources for configuring the NPK sensor. (6 Hours)
Discuss over Discord goals and workload split for the week (2 hours)
Week 9
10/24/2024
Update Website (2 hours)
Tested the PCF8574 I/O expander board with an Lamp light (1.5 Hours)
Meet in person and continue assembly/debugging (5 hours)
10/23/2024
Code debugging and testing (3 hours)
Analyzed responsiveness issues on the display (2 Hours)
10/22/2024
Wire mapping and GPIO extension testing (4 hours)
Troubleshot graphical data display issues. (4 Hours)
10/21/2024
Test stepper motors wiring and railing (4 hours)
10/20/2024
Found CRC addressing requirements in the NPK sensor manual. (2 Hours)
Meet in person and assemble/debug (4 hours)
10/19/2024
Build new ball screw assembly and third smart plug (3 hours)
Tested different libraries to facilitate communication with the NPK sensor on the R4. (5 Hours)
Coordinate over discord goals and meeting times (1 hour)
10/18/2024
Attempt to fix previous ball screw assembly (1.5 hours)
Researched common NPK sensor issues and identified compatibility challenges with Arduino R4. Reviewed manufacturer resources for possible solutions. (4 Hours)
Week 8
10/17/2024
Plant control group and experiment group (1.5 hours)
Reviewed overall progress, last minute modifications. (2 Hours)
10/16/2024
Update website sections (2.5 hours)
Implemented safety feature for pump operation limits; created a duration selection screen. (5 Hours)
Sensor and railing assembly (3.5 Hours)
10/15/2024
Continue work on wiring (2 hours)
Organized manual controls for fans, lights, and pumps on the right side of the display. (6 Hours)
10/14/2024
Wiring all individual parts together (2 hours)
Meet in person and work on frame (5 hours)
10/13/2024
Connect lights to smart plug (1.5 hours)
Organized manual controls for fans, lights, and pumps on the right side of the display. (4 Hours)
Meet over discord (1.5 Hours)
10/12/2024
Work on fluid piping to get pumps working (2 hours)
Positioned real-time sensor data on the left side for immediate visibility. (2 Hours)
10/11/2024
Focused on overhauling the UI layout based on Professor Notash's feedback. (4 Hours)
Week 7
10/10/2024
10/9/2024
10/8/2024
Explored troubleshooting options for the NPK sensor, considering coding adjustments or new hardware. (3 Hours)
Continue previous discussion over discord ( 1.5 hours)
10/7/2024
Update website sections (2.5 hours)
10/6/2024
Attempt to fix linear actuator (3 hours)
Diagnosed issues with the NPK sensor, discovered potential inherent problems with the sensor. (6 Hours)
Meet over discord and discuss issues with linear actuator and NPK sensor (3 hours)
10/5/2024
Construct top chamber (2 hours)
Tested motors through code using the Stepper library, configuring stepper motors for rotation. (4 Hours)
10/4/2024
Work on linear actuator rotation (2 hours)
Simulated motor steps to ensure software functionality (5 Hours)
Week 6
10/3/2024
Troubleshoot linear actuator rotation problem (2 hours)
Software Bug Fixes (1.5 Hours)
10/2/2024
Sand and paint wood pieces, trim sheet metal edges (2 hours)
Jon improved the manual controls for the fans, pump, and light. (1 Hour)
10/1/2024
Epoxy additional frame pieces (1 hour)
Solved problem where the display didn’t clear previous data, causing overlapping visuals. (5 Hours)
9/30/2024
Shop for hardware solutions to assembly obstacles (1 hour)
Integrated the NPK sensor data into the display, replacing redundant moisture sensor data. (1.5 Hours)
9/29/2024
Additional frame assembly - fans and edges (2 hours)
Meet in person and continue assembly of frame (5 hours)
9/28/2024
Worked on implementing the graphical data display for the project. (2 Hours)
9/27/2024
Research fluid tube shutoff valve options (2 hours)
Tried to solve problem where the display didn’t clear previous data, causing overlapping visuals. (5 Hours)
Discussed Meetup times and individual work for the week (1 Hour)
Week 5
9/26/2024
Tested 12V fans with automatic temperature-based speed control, aligning with the design’s automation goals. (2.5 Hours)
Meet with Professor (1.5 hours)
9/25/2024
Update Progress Log and Website (4 Hours)
Researched and applied a method to graph sensor data using angled lines, based on a YouTube tutorial, though some bugs remain to be resolved. (1 Hour)
Update website and coordinate schedules (2 hours)
9/24/2024
Continue work on final report (3 hours)
Implemented a solution to store averaged sensor data over time using the Arduino millis() function and arrays, allowing for historical data access. (1.5 Hours)
9/23/2024
Construct linear bearing and test with a drill to simulate stepper motor (2 hours)
Managed pixel-by-pixel updates to display and erase elements, addressing memory strain due to real-time data redraws. (4 Hours)
Met to continue constructing frame (3.5 Hours)
9/21/2024
Research linear bearing construction and stepper motor functionality(3 hours)
Purchase overlooked parts for sensor mobility arm (1 hour)
9/20/2024
Attach grow lights to frame (1 hour)
Worked on enabling the touch feature of the RA8875 display by manually scaling the x and y values using the map() function. (3 Hours)
Discuss group goals for upcoming week (2 hours)
9/19/2024
Cold weld sheet metal to frame (1.5 hours)
Week 4
9/18/2024
Update Progress Log and Website (2 Hours)
Researching graphical data logging implementation (3 Hours)
Ensuring proper fit for components within the frame & Extending the frame according to the approved plan (4 Hours)
9/17/2024
Work on final report (2.5 hours)
Troubleshooting touch input functionality (4 Hours)
9/16/2024
Designing and implementing the initial UI layout (5 Hours)
Constructing the project frame (cutting and shaping sheet metal (5.5 Hours)
9/15/2024
Construct second smart plug outlet (3 hours)
Getting the TFT display operational (4 Hours)
9/14/2024
Cut sheet metal and spray paint buckets (2 hours)
Desoldering/soldering the RA8875 driver connections (3.5 Hours)
9/13/2024
Shop for materials for frame extension (3 hours)
Researching limitations and optimizing graphics (RAM) & Iterative pixel alignment and layout adjustments (8 Hours)
Project Discussion over Discord (1 Hour)
9/12/2024
Meeting with the professor to discuss task priorities (2 Hours)
Week 3
9/11/2024
Update Progress Log and Website (2 Hours)
Update Progress Log and Website (2 Hours)
Check in before the group meeting (1.5 Hours)
9/10/2024
Continue Sensor Troubleshooting (3 Hours)
Troubleshooting with the 7.0" TFT display connection to the RA8875 driver. (3.5 Hours)
9/9/2024
Soldered pins on the RA8875 driver to connect it to the breadboard. (3 Hours)
9/8/2024
Build Smart Plugs (5 Hours)
Completed physical setup of moisture, temperature/humidity, water level, and display system. (2 Hours)
Research and Order Parts (1 Hour)
9/7/2024
NPK Sensor Troubleshooting (5 Hours)
9/6/2024
Discuss Frame and OLED options (2 hours)
9/5/2024
Research Frame Options (2 Hours)
Worked on getting the capacitive moisture sensor to function correctly. (3 Hours)
Meet with Professor Notash (1.5 Hours)
Week 2
8/29/2024
Troubleshoot LCD display (2 hours)
Meet and discuss next weeks goals (2 hours)
9/4/2024
Update progress log (2 hours)
Update progress log (1 hours)
Discuss website updates and prepare for weekly meeting (1.5 hours)
9/3/2024
Wire NPK sensor and troubleshoot code (3 hours)
Planned testing for the RA8875 driver and 7.0" TFT display. (1.5 Hours)
Recap progress and troubleshoot problems (2 hours)
9/2/2024
Assemble NurtureNest Frame and continue work on LCD display (2 hours)
Researched proper wiring for the RA8875 driver and Arduino SPI interface. (2.5 Hours)
9/1/2024
Discuss progress and roadblocks (1 hour)
8/31/2024
Simulated the components in Tinkercad. (1.5 Hours)
8/30/2024
Visit local stores for misc. parts (2 hours)
Coded for the pumps, fans, and moisture sensor. (2 Hours)
Week 1
8/28/2024
Update progress log (2 Hrs)
Updated Design Progress Log and Time & Effort Table (3 Hrs)
Check in before weekly meeting (0.5 Hrs)
8/27/2024
Update design portions of the website(3 Hrs)
Updated Proposal Progress Log and Final Proposed Diagram/Rendering (2.5 Hrs)
8/26/2024
Visit Skycraft to browse components (1.5 Hrs)
Updated Time & Effort Table (2.5 Hrs)
Finalize frame decision (2 Hrs)
8/25/2024
Soil saturation Testing (3 Hrs)
Code Debuging (4 Hrs)
8/24/2024
Research microcontroller controlled plugs (2 Hrs)
Wired/coded Temperature and Moisture Sensor on Bench (4.5 Hrs)
Discuss frame options (0.5 Hrs)
8/23/2024
Researched library/dependencies (2.5 Hrs)
Recap meeting and split responsibilities (0.5 Hrs)
8/22/2024
Order parts from Amazon (0.5 Hrs)
Tinkcad Circuit Simulation (3.5 Hrs)
Meet with Professor Notash (1.5 Hrs)